I was able to return to the Spotlight Development site located at the Belmont / Breakwater inter-junction in order to meet with the project manager, Chris. This was really insightful into the construction of concrete tilt up panels. I was able to determine that the size of my strip footing for the major project would be 600mm x 600mm with 6-12TM. This was based on similar sized panels framing the structure of the retail blocks which would in turn have similar loads as those in my showroom structure.

The drawings also demonstrate possible ways of connecting the RC Slab on Ground with the wall panel using Cast-In Plates. One of the other details also shows how a suspended slab could be attached to the panel using a dowel and ferrule system – a possible method that could be employed for the major project.